October 8, 2026
How long should it take to build 808 feet of path? For the Jones Creek Greenway, the missing piece between Lake Hogan Farm Road and the Twin Creeks Greenway, the answer has run past every date anyone gave for it. The town's own description of the project is modest. It calls for an approximately 808-foot paved multi-use path and pedestrian bridge to connect Lake Hogan Farm Road with the existing Twin Creeks Greenway, which runs north to the parking lot at Morris Grove Elementary School.
Design is not what's holding it up, and neither is public opposition. The delay now sits in contracting, the stage between an approved plan and a crew on site. The destination at the far end has stalled too. Twin Creeks Park has a master plan but almost no money to build it. The connection will likely open well before the park it was designed to reach.
Half of this route already exists. The first segment of the Jones Creek Greenway was finished in 2011. It runs from the future Twin Creeks Park, also known as Moniese Nomp Park, to Morris Grove Elementary. The unbuilt piece is the short stretch that would tie that segment to Lake Hogan Farm Road.
Carrboro's January 2026 transportation update lists who the link is for. It says the project "will provide off-road walking and cycling options for the Lake Hogan Farms, Legends, Ballentine, and Fox Meadow neighborhoods to destinations such as Morris Grove Elementary and the future Twin Creeks Park." In other words, the path that already reaches the school ends short of the streets it was meant to serve.
The project is identified as C-5181 in state and regional records. Read in order, those records show a design that kept moving forward while the construction start kept moving back.
| When | What the record says |
|---|---|
| 2009 | Carrboro adopts the Bolin Creek Greenway Conceptual Master Plan, which includes the Jones Creek corridor |
| 2011 | First Jones Creek segment completed, from future Twin Creeks Park to Morris Grove Elementary |
| August 14, 2023 | Project's environmental document approved |
| October 18, 2023 | Town notice says construction of the connection is "expected to begin next year" |
| February 19, 2024 | Planning director reports design at 90 percent, after public hearings at 30 and 60 percent |
| January 2026 | Town update schedules final plan submission for May 2026, followed by advertising for construction |
| March 26, 2026 | Let/start date listed in the county's project table |
| May 18, 2026 | County table: final plans approved by NCDOT, "Awaiting letting," estimated completion FY2027, cost $910,000 |
| June to September 2026 | No contract award for the project on Carrboro Town Council agendas |
The May row stands out. The listed let date of March 26, 2026 had already passed, and the status still read "Awaiting letting." The Council agenda for June 2 had no award item for the greenway. Neither did the June 16 agenda, which instead awarded a contract for a separate street-resurfacing project. The July 7 meeting was a closed session only. The town's posted calendar shows no August Council meeting. The September 15 agenda had no award either. As of the end of September 2026, no public record sets a construction start date.
Carrboro's January update lists what happens between approved plans and construction. It's a chain of approvals, and each one waits on the one before it:
By the May county table, the project had reached NCDOT approval of its final plans. The NCDOT steps exist because the project uses federal money. The town amended its municipal agreement with NCDOT to add federal funding and update the schedule.
The Morgan Creek Greenway Phase 1, across town, shows how long the later steps can take. That project was advertised for construction on November 23, 2025, and four firms bid when bids opened on December 18, 2025. Staff then prepared a January 2026 Council item to award the contract. Even with bids in hand, the same May 2026 county table puts Morgan Creek's estimated completion at FY2028. Jones Creek's FY2027 estimate covers the fiscal year that ends June 30, 2027, and the project has not yet been advertised for bids. That estimate leaves a narrow window.
The bridge is the expensive part of a short project, and the town put it there on purpose. In 2024, Carrboro Town Council member Randee Haven-O'Donnell told The Daily Tar Heel why the path can't simply follow the ground:
"It needs a bridge to span the most impactful areas that, without a bridge, they would be compacted and hardened and impact the wildlife and the wetland organisms that live there."
The same article reported that people who commented gave positive feedback on the Jones Creek design and found it minimally invasive to open space. The town had also held walking meetings on the site. Greenways along Bolin Creek have been debated more. The Friends of Bolin Creek argued in 2023 that the broader greenway plan reaches into the creek's riparian buffer. Haven-O'Donnell noted that Bolin Creek is much larger than Jones Creek. The Jones Creek link has avoided that larger debate. What's left for it is paperwork.
The town update names the future Twin Creeks Park as one of the link's destinations. That park is much further from opening than the path.
A summary of a meeting of the Orange County Parks and Recreation Council, published with the council's September 2, 2026 agenda, gives the background. Twin Creeks Park is a 193-acre site north of Carrboro that the county bought in 2001 to serve as a future district park. A master plan exists, but the county's Capital Investment Plan has no money for the park beyond $140,000 for farmhouse repairs.
At that meeting, Nick DiColandrea and Marcey Fisher presented a proposal from Piedmont Wildlife Center. The nonprofit started as a wildlife rehabilitation clinic and now focuses on environmental education. It wants to turn the Twin Creeks farmhouse and barn into part of its operations base and use the surrounding grounds for nature programs. The center currently works out of a farm owned by Durham County, where it has limited room to grow. The summary describes the partnership as a way to develop the site "in a new and different but related context." Council members asked about funding, development timeline, and programming, and voiced general support. It's still a proposal. No agreement, opening date, or construction schedule is attached to it.
The Jones Creek link has approved plans, a $910,000 cost estimate, and a target fiscal year. The park it leads toward has land, a master plan, and a farmhouse repair line. If the bridge opens on anything close to its current schedule, it will reach the edge of a park that is still mostly undeveloped. Carrboro's planning director, Trish McGuire, said in 2024 that she expected more connecting bridges after Twin Creeks Park is built. The park's timeline will set the pace for those.
The Jones Creek link heads north toward the school. A second planned piece would come back south into Lake Hogan Farms. Carrboro describes Phase 2 of the Bolin Creek Greenway as running from the southern end of the Jones Creek Greenway southeast, across Turtleback Crossing Drive, to the existing Lake Hogan Farm trail network north of Hogan Woods Circle. The town won Regional Flexible Funds for Phase 2 design in the FY25 call for projects, and that money should be available in FY27.
That funding covers design only. No construction date or completion estimate has been published for Phase 2. The town's 2023 notice also said later phases would connect the Fox Meadow and Winmore neighborhoods. If the plans hold, the network would eventually link the neighborhood's trails, the Jones Creek bridge, the Twin Creeks Greenway, and Morris Grove Elementary. Every piece south of the 2011 segment is still in design or contracting.
The next thing to watch for is a Carrboro Town Council agenda item awarding the construction contract for C-5181. That item would also put the first real date on the project.
If you live off Lake Hogan Farm Road and you're weighing how this path, the Twin Creeks plans, or the Phase 2 route might shape your plans for your home, Ray Posada Real Estate can go through the public records with you and explain what each stage means and what's still uncertain. Contact Us whenever it's useful to talk it through.